SINCOR DOWNSTREAM PROJECT

Site Preparation

Contracting Party:

Oriente Petrochemical Complex. Venezuela

Location:

Sincrudos de Oriente, S.A. (SINCOR)

Execution date:

Feb 1998 - Feb 2000

Work done:

Earth moving; drainage works; canalization of the Hoces River.

• Total volume of earth moving: 2,428,855 m3
• Structural concrete: 16,526 m3
• Steel: 1,053,064 Kg
• Concrete pipes: 4,820 ml